Which time is associated with elements of a setup procedure performed while the process or machine isn't running?

Prepare for the APICS CPIM Exam 1. Use flashcards and multiple-choice questions to boost your understanding of planning and inventory management. Equip yourself with hints and thorough explanations to ensure exam success!

Multiple Choice

Which time is associated with elements of a setup procedure performed while the process or machine isn't running?

Explanation:
Setup activities are divided into internal and external. Internal setup time is the portion that must be done when the process or machine is not running, such as changing tooling, swapping parts, or adjusting equipment before starting the next run. External setup time consists of tasks that can be completed while the machine is still operating or between runs without stopping production, like preparing the next job or gathering tools in advance. The total changeover time includes both internal and external components, while idle time is simply downtime with no production. Since the tasks in question must occur while the machine isn’t running, they are internal setup time.

Setup activities are divided into internal and external. Internal setup time is the portion that must be done when the process or machine is not running, such as changing tooling, swapping parts, or adjusting equipment before starting the next run. External setup time consists of tasks that can be completed while the machine is still operating or between runs without stopping production, like preparing the next job or gathering tools in advance. The total changeover time includes both internal and external components, while idle time is simply downtime with no production. Since the tasks in question must occur while the machine isn’t running, they are internal setup time.